    Historical data validity in IT Services

    Hello all.

    I have successfully implemented IT Services, but I have a doubt.

    Let's assume I have data stored from 30 days ago, and I set up the IT Service one week ago. If I click on "Graph (show)", it displays the attached image, where you can only green bars.

    ¿Does it mean that my IT Service is OK from all 30 days backwards? I mean, ¿does Zabbix calculate the IT Service backwards in time previous to its setup?

    ¿From when can I assume the IT Service data as valid?

    Thanks in advance!
    Attached Files
    Last edited by banderas20; 29-10-2009, 17:31. Reason: forgot attachment
  • alixen
    Senior Member
    • Apr 2006
    • 474

    #2
    Hi,

    This is a known problem.
    Zabbix will happily report that your service was OK even in 2003.
    See my post http://www.zabbix.com/forum/showpost...9&postcount=15. It was about IT services in Zabbix 1.4 but, although it has been greatly improved in 1.6, this problem still remains.
    I don't know if it has been fixed in 1.8.

    Regard,
    Alixen
    http://www.alixen.fr/zabbix.html

    Comment

    • banderas20
      Member
      • Jun 2009
      • 30

      #3
      Hi, Alixen.

      I suposed that. I'm running v.1.6.6 and still have that problem.

      At least now I know the problem does exist, and that I can't rely on previous values.

      Thanks!

      Comment

      • zabbix_zen
        Senior Member
        • Jul 2009
        • 426

        #4
        This issue should be undoubtedly fixed, if not in Z1.8 then in Z1.8.1

        Don't also forget that that SLA graph shows you the % of time a particular Service/Service aggregate was kept without crossing the threshold you specified